Blackstone Trip, March 2017

By: ksterne  on: Mon., Apr. 10, 2017 02:00 PM EDT  (573 Reads)
Following the November 2016 trip, the correct size (5/8” rod) of CADweld mold was ordered in order to complete the grounding work that had been long overdue. However, winter cold and wet set in and so the work could not be completed until better temperatures arrived. In the month prior to this trip the internet connection to the site had been out for several days if not weeks at a time going on 3 to 4 weeks. So with these issues, a trip was planned to take care of these issues and make sure the radar was running fairly well (with known issues on the antennas).

Fort Hays Reflector Wire Repair Trip, Feb. 2017

By: ksterne  on: Mon., Feb. 27, 2017 01:38 PM EST  (774 Reads)
Hays, KS sustained a major freezing rain and icing event in mid-January 2017. Following reports from FHSU student intern, Brett Chrisler, of significant damage to the West main antenna array a trip was made by engineer Kevin Sterne to assess the damage at the radar site. As well, this trip would be allow for preparations to be made for a future repair trip.

Blackstone Trip, Nov. 2016

By: ksterne  on: Mon., Nov. 07, 2016 03:34 PM EST  (1452 Reads)
After many, many years, the grounding work along the antenna poles had not been completed. On each antenna pole, a ground rod had been driven into the ground and a copper busbar had been attached under one of the bolts on the base of the pole. So a trip was made to the site by Kevin Sterne, Shibaji Chakraborty and Muhammad Rafiq to complete the grounding work.

Blackstone Trip, July 2016

By: ksterne  on: Fri., Sep. 02, 2016 03:17 PM EDT  (1577 Reads)
Brett Chrisler, the Fort Hays State University student intern, made a trip to the Blacksburg SuperDARN lab in early July. During his trip, Brett would review research areas that he can explore with our group as well as to make a trip to the Blackstone radar to show him another style of SuperDARN radar and gain more hands-on training.

Goose Bay Trip, June 2016

By: ksterne  on: Fri., Sep. 02, 2016 03:10 PM EDT  (867 Reads)
The replacement of the ground coax is a longstanding project that needed to be completed at Goose Bay. In preparation for this project, a work order was placed with Serco to clear all the trees and brush that have taken over the antenna array grounds over the years.

Blackstone Trip, Jan. 2016

By: ksterne  on: Wed., Jan. 27, 2016 11:07 AM EST  (2867 Reads)
Shortly before the winter break, the internet connection to the radar site went down. Being patient since the availability of people to check on it would probably be low, the connection remained off over the two week winter break. However, our local contact was able to check on the connection for us and noted that the Power-over-Ethernet (PoE) power supply had melted and thus the internet connection was broken. The damage to the PoE unit and the RJ45 connector can be seen in the picture. In order to keep the linux computer’s hard drive from filling up, a trip to the radar site was made to restore the connection. In addition, this trip would be used to install the newly acquired and configured linux computer.